Phone: 613-628-3101 ext 2855
Works Superintendent: Jason Zohr
Public Works Administrative Assistant: Dana Barkley
County of Renfrew's Transportation Master Plan
Asset Management Plan - Road Network
Road Network - Table 1 - Forecasting Condition Rating Example
The Township of Bonnechere Valley's main construction project for 2024 will be the rehabiliation of Zadow Road. Through our tender process the contract has been awarded to McCrea Excavating Ltd. We will be making improvements to approximately 2.3 km of Zadow Road from Silver Lake to Ruby Road.
Zadow Road as well as Clee Road will be closed except to local traffic beginning August 6, 2024 (weather dependent) to September 27, 2024 from 7 am to 9 pm, Monday to Friday with the potential of Saturdays.
This project is made possible through the support provided by the Province of Ontario's Community Infrastructure Fund (OCIF).